Reduced EP. Increased total life of cyclone.

Tramp inclusion resulted in constant plant stoppages due to metal detection and also damaged existing alumina lined cyclones, which required constant repair due to tile damage.

The HICTECH team designed and manufactured replacement 27% chromecast cyclones.

The result for the client has reduced stoppages and increased productivity, and the lifespan of the cyclone increased from 36 to 58 weeks.